Baseline

Represented by triple constraints: the original project plan scope, time duration, and costs plus approved changes. Is important to remember that if the plan changes, those changes become part of the project baseline once they have been approved.

For example, if your project was to build a bookshelf with two shelves, and the customer decides that they want four shelves, should the project performance be measured against the two-shelf plan or the four-shelf plan?